euroBLADE

installation info

Direct Fixing (suggested method)

Panels with horizontal matt-black substrates are direct-fixed to installed horizontal wall battens.

EB2WallsVBD_DirectFix

Plan section showing batten direct fixing

 

Black screws are used so that the black coloured screw head is hidden in the spacing between the battens.

EB2WallsVBD_DirectFixPlan

Split Batten Fixing

Panels with horizontal substrates are installed using split battens fixed to the back of the panel, interlocking with split battens fixed to vertical wall battens.

EB2WallsVBD_SplitBF

Plan section showing split batten fixing

EB2WallsVBD_SplitBFPlan

downloadbutton

 

Direct Fixing (suggested method)

Panels with vertical matt-black substrates are direct-fixed to installed horizontal wall battens.

 

EB2WallsHBD_DirectFix

Plan section showing batten direct fixing

 

Black screws are used so that the black coloured screw head is hidden in the spacing between the battens.

EB2WallsHBD_DirectFixPlan

Split Batten Fixing

Panels wtih small split batten blocks fixed to matt-black substrates are installed to split battens fixed to vertical wall battens.

EB2WallsHBD_SplitBF

Plan section showing split batten fixing

EB2WallsHBD_SplitBFPlan

downloadbutton

 

Direct Screw Fix to Grid – from below

Panels are secured by fixing from the underside, through the matt-black substrate into the furring channel using black screws hidden in the spaces between the battens.

EB2CeilingDS_FromBelow

Plan section showing direct screw fix to grid – from below

EB2CeilingDS_FromBelowPlan

Direct Screw Fix to Grid – from above

Panels are secured from above the grid, by screwing down through the furring channel into the back of the substrate crossmembers.

EB2CeilingDS_FromAbove

Plan section showing direct screw fix to grid – from above

downloadbutton